The objective of this AIP-SUP to inform the relevant personnel about the penetration of obstacle limitations surfaces of LHBP airport by cranes erected between the centrelines of RWY 13L/31R and RWY 13R/31L on the southern side of Terminal 2.
As a part of the airport development plan a construction of a new hotel building has been started next to the existing one, on the southern side of terminal 2 buildings.
During the construction period a crane garden is activated. The number of cranes are between 1 and 4 depends on the status of construction.
The crane garden is active:
From : 06:00 7th of December 2023
To : 18:00 14th of October 2024.
Operational period : H24
The coordinates of the centre position of the crane garden is : 47°25’50.10”N 019°15’47.06”E.
The radius of the crane garden is : 80 m from the centre position.
Top elevation of the highest crane is : 186 m AMSL.
Due to height of cranes the inner horizontal surface of the airport obstacle limitations surfaces are penetrated!
All cranes included the booms are marked by red and white strips and lighted by low intensity red obstacle lights according to ICAO ANNEX 14.
In case of the lights are inoperative or other relevant information please contact the airside management of Budapest Airport Pte. Ltd. using the following email address:
Email:airside.bud@bud.hu
This SUP replaces the following NOTAM: A5683/23