The Demolition of disused paved surfaces at LHDC:
The demolition project starts in Q2 2023 and the competition is scheduled for the Q1 2024. The works are phased and the relevant information for each phase will be disseminated by AIP supplement and activated by NOTAM. The
may be published by NOTAM.
Commence and actual finish of the phase will be notified by NOTAM.
No movement areas are involved in this phase.
No traffic restrictions are expected at phase A.
Commence and actual finish of the phase will be notified by NOTAM.
Involved areas: TWY A, TWY B, APRON.
Restrictions on TWY A:
Commence and actual finish of the phase will be notified by NOTAM.
Involved areas: RWY 04R/22L, TWY A.
Restrictions on TWY A:
Restrictions on RWY 04R/22L:
Commence and actual finish of the phase will be notified by NOTAM.
Involved areas: RWY 04R/22L, TWY A.
Restrictions on TWY A:
Restrictions on RWY 04R/22L:
Commence and actual finish of the phase will be notified by NOTAM.
Involved areas: RWY 04R/22L.
Restrictions on RWY 04R/22L: